Project Overview
- Equipment: Liebherr LTR 1220 Lattice Boom Crawler Crane
- Main Load: Lower carriage with crawler tracks — 95,000 lbs
- Width: 15 feet with tracks attached
- Height: 13 feet 2 inches
- Convoy: 3 trucks (carriage, boom sections, counterweights)
- Origin: Savannah, Georgia
- Destination: Los Angeles County, California
- Distance: ~2,400 miles
- States Permitted: GA, AL, MS, LA, TX, NM, AZ, CA
- Trailer Type: 7-axle lowboy (main load) + 2 step-deck trailers
- Transit Time: 12 days origin to delivery
Key Metrics
States Permitted
8 States
Separate Loads
3 Trucks
Delivery Status
On Schedule
Background: Cross-Country Crawler Crane Transport
Crawler cranes present a unique challenge in heavy haul: they are large, expensive, often irreplaceable on the project timeline, and must be moved in multiple disassembled loads that need to arrive at the same destination within a narrow reassembly window. The Liebherr LTR 1220 is a 220-ton capacity lattice boom crawler crane used in large-scale construction, wind energy, and petrochemical projects. In transport configuration, it is broken into at minimum three separate loads — the lower carriage with tracks, the boom sections, and the counterweight plates — each requiring its own oversize permit, its own trailer configuration, and its own driver.
This project was initiated by a specialty crane contractor relocating an LTR 1220 from a completed industrial project at the Port of Savannah, Georgia, to a construction site in Los Angeles County, California, where the crane was needed for a large utility infrastructure project. The receiving site had a tight mobilization schedule, and the crane contractor needed all three loads to arrive within a 48-hour window to allow rigging crews to begin reassembly without delay.
R&RM LLC has been coordinating complex heavy equipment moves since 2011 — including multi-load convoys where the components of a single machine travel separately across state lines and must converge at the destination. This case study outlines how we managed the planning, permitting, and execution of this 2,400-mile cross-country crane relocation.
The Challenge
Eight-State Permit Coordination for Three Separate Loads
Each of the three loads required its own permit application in all eight transit states: Georgia, Alabama, Mississippi, Louisiana, Texas, New Mexico, Arizona, and California. That is 24 individual permit applications, each with state-specific forms, dimensional requirements, and processing windows. Texas alone required separate TxDOT district permits for the sections of the state highway system in different TxDOT districts — a detail that catches carriers unfamiliar with Texas oversize permitting off guard and can add days to a move if not anticipated.
California's Caltrans permit process for the main load (15 feet wide, 95,000 lbs) required a route survey and confirmation from Caltrans that the designated local route from the nearest state highway to the project site was structurally adequate. California is one of the more rigorous states for final-mile clearance on oversize loads, and this review added time to the permit process that we had budgeted for in the project schedule.
Bridge Clearance Planning on the I-10 Corridor
The primary route — I-10 west from the Georgia-Alabama border through Mississippi, Louisiana, Texas, New Mexico, and Arizona into California — is one of the most commonly used heavy haul corridors in the country. However, at 15 feet wide with the LTR 1220's crawler tracks attached, the carriage load exceeded the standard oversize lane width for several bridge structures in the Louisiana and Texas segments where lane widths narrow on elevated sections.
We requested bridge clearance data from Louisiana DOTD (Department of Transportation and Development) and TxDOT for the specific bridges on our permit route. Three bridges in the Louisiana segment and one in the Texas segment required a lane configuration review: our carrier would need to occupy two full travel lanes temporarily at those crossings, requiring traffic control measures coordinated with the state DOT. We applied for the necessary traffic control permits concurrent with the load permits and confirmed the coordination window with each state's permit office before finalizing the move date.
Arizona Summer Heat and Load Timing
The move was scheduled in midsummer, which introduced a specific concern for the Arizona segment: ADOT (Arizona Department of Transportation) imposes seasonal heat restrictions on oversize loads on certain highway segments, particularly in the Phoenix metro area and along I-10 west of Phoenix where pavement temperatures can affect load limits on weight-sensitive roads. We reviewed the applicable ADOT seasonal restrictions for the planned route and confirmed that travel outside peak heat hours — departing before 6:00 AM in the Phoenix segment — would keep the convoy within the permitted parameters. The nighttime move through Phoenix also had the practical advantage of reduced traffic volume on the metro freeway system.
Our Solution
Pre-Move Planning: 21-Day Lead Time
Given the complexity of 24 permit applications across 8 states with concurrent traffic control coordination in 2 states, we established a 21-day planning window before the target departure date. Permit applications for California and Texas were submitted first, as those states had the longest review cycles. Georgia, Alabama, Mississippi, Louisiana, New Mexico, and Arizona applications followed in parallel as soon as Texas and California confirmed the route review timeline.
We also coordinated with the crane contractor's rigging crew to confirm the disassembly sequence and the dimensions of each load in transport configuration — critical for permit accuracy. An error in stated width or height at the permit application stage can result in a permit that does not cover the actual load, which creates enforcement risk at the point of a roadside inspection. We reviewed the manufacturer's transport dimension specifications directly and compared them against the rigging crew's measurements of the crane in its as-configured state before any permit applications were filed.
Trailer Configuration for Each Load
The three loads required three different trailer configurations:
- Lower carriage with crawler tracks (95,000 lbs, 15 feet wide): 7-axle lowboy with 3-axle jeep. This configuration distributed the weight over enough axles to satisfy bridge formula requirements while keeping the load height within the vertical clearance limits on the permitted route.
- Boom sections (9 sections, each under 48,000 lbs, 14 feet wide): Step-deck trailer with outrigger pads and blocking configured for the tubular boom geometry. Boom sections were bundled and secured with certified strapping configurations reviewed by the crane manufacturer's transport guidelines.
- Counterweight plates (aggregate weight 52,000 lbs, 12 feet wide): Step-deck trailer with steel plate load securement. Counterweight plates were stacked and blocked to prevent lateral shift, with corner chains providing redundant securement at each stack.
Convoy Coordination and Staggered Departure
All three trucks did not depart simultaneously. We staggered departures by 6 hours between trucks to avoid convoy bunching on the highway system — a convoy of three oversize trucks spaced less than 500 feet apart triggers additional permit requirements in some states and creates traffic disruption disproportionate to the load. Staggered departures allowed each truck to operate effectively as a solo oversize move within the state permit windows while maintaining communication between drivers via cell phone and our dispatch.
A shared arrival window of 48 hours at the destination was maintained by adjusting overnight stop timing on each truck's individual schedule. The counterweight truck — the fastest-moving load due to lighter weight and narrower width — was dispatched last and instructed to hold at a staging point outside Los Angeles until the main carriage and boom truck had arrived, so that all three loads were on-site simultaneously for the rigging crew's mobilization.
Final-Mile Delivery in Los Angeles County
The delivery site in Los Angeles County required the oversize convoy to exit the state highway system and travel approximately 4 miles on county and local roads. Caltrans had reviewed and approved this segment as part of the permit, and we coordinated with the county public works office to confirm road weight limits and clearances on the specific route. A utility line lift was required at one intersection where overhead communications lines dropped below the 13-foot-2-inch height of the loaded carriage trailer. We coordinated the lift with the utility company and the Los Angeles County Sheriff's Department for traffic control during the crossing.
Execution and Delivery
The convoy departed Savannah over three consecutive mornings. All three trucks completed the Louisiana segment during a single travel window coordinated with Louisiana DOTD for the two-lane bridge crossings requiring traffic control. The Arizona nighttime departure through Phoenix proceeded without incident, with ADOT's permitted travel window accommodating the early morning schedule.
The carriage truck arrived at the Los Angeles County site on day 11. The boom truck arrived the same afternoon. The counterweight truck, which had held overnight at a staging area in Fontana, California, delivered to the site the following morning — within the 48-hour window. The crane contractor's rigging crew commenced reassembly the same day the final load arrived.
Total transit time for the convoy: 12 days from first departure to final delivery. All three loads arrived without damage. All permits were honored without enforcement action or route deviations across all eight states.
Results
- Delivery: All three loads arrived within the 48-hour reassembly window as required by the crane contractor
- Permits: 24 individual permits across 8 states, all approved in advance of departure
- Compliance: Zero violations or enforcement stops on any of the three loads across all eight states
- Safety: No incidents, no load shifts, no damage to equipment or infrastructure
- Project Impact: Rigging crew mobilization began on schedule; crane was operational within the project's construction timeline
Key Takeaways for Cross-Country Crane Transport
Multi-state crane moves require more lead time than any other category of heavy haul transport. Permit processing, bridge clearance review, traffic control coordination, and utility line lift scheduling all run on different timelines controlled by different agencies. A carrier that submits permit applications sequentially — waiting for one state to approve before applying to the next — will routinely miss project windows. Parallel processing across all states simultaneously, with contingency time built in for each state's review cycle, is the only reliable approach for 8-state moves.
Crawler crane width in transport configuration is frequently underestimated. The track shoes on large crawler cranes extend the overall width well beyond the machine's rated operating width, and the transport width must be measured in the actual as-configured state rather than derived from the spec sheet. An overestimate results in a permit for a wider load than you have, which is generally acceptable; an underestimate results in a permit that doesn't cover the actual width, which is a regulatory violation. Always measure before you apply.
California's final-mile clearance process is more involved than most other states, particularly for loads above 15 feet wide or requiring a route deviation from the standard oversize route survey. Build Caltrans review time into your project schedule as a fixed constraint, not a variable. For the most complex loads, Caltrans may require an engineering review that other states do not.
For crane transport or other complex multi-load oversize moves, contact R&RM LLC to discuss the permitting timeline, trailer configurations, and coordination requirements specific to your project. We serve all 48 continental states with oversize load transport and multi-state permit coordination.
Moving a Crane or Complex Equipment?
R&RM LLC coordinates multi-load convoys, multi-state permits, and utility line lifts for large equipment transport across all 48 continental states. In business since 2011.
Related Services & Resources
Oversize Load Transport
Pilot cars, route surveys, and state-by-state oversize permits for loads exceeding standard legal dimensions.
Crane Transport
Crawler cranes, tower cranes, and boom trucks — transport configurations and permit requirements explained.
Permit & Escort Services
Multi-state permit coordination, pilot car arrangement, and traffic control for complex oversize moves.